Project Summary: Supply and installation of 1500kVa Secondary Crusher Transformer at Evolution Mining, Mount Rawdon Project
Client: Evolution Mining – Mount Rawdon Operations
Timeframe: Installation January 2017
Project Summary: Perform infraspection and provide report on efficency of Double Skinned Exhaust and Turbo & Exhaust Lagging
Client: Aletek Advanced Exhaust Technologies
Timeframe: September 2022
Project Summary: Design, manufacture and installation of 6.6kV/433V stainless steel portable substation for Decant Dam evaporator pump/sprays supply and associated HV cabling at Evolution Mining, Mount Rawdon Project
Client: Evolution Mining – Mount Rawdon Operations
Timeframe: Installation January 2022
Project Summary: Relocated and refurbished 1.5MVa oil-filled transformer, redesigned, manufactured and replaced HV air box, added flanges to radiators to necessitate quick removal and ease of transport and placement, removed and replaced all gaskets and repainted with high build epoxy and polyurethane coatings.
Client: Bundaberg Sugar Pty Ltd
Timeframe: Installation January 2022